20.
Snow stopped
play, but not without an excuse for bubbles
I’m
really sorry I missed the usual Sunday slot.
Not very good I know after leaving you all on tender hooks to see if we
could complete the action packed week or not.
You’re
obviously all thinking – NOT! You’re
right – sort of.
The
week started off well with Max, Stefan and Jake flattening off the ground
inside the building in preparation for the damp proof membrane (DPM). It looks really good – the rooms look more
like rooms with a flat floor, and everything looks a bit tidy. Always fills me with delight.
On
Tuesday afternoon I started cutting the large ‘radon proof’ rolls down to
size. The trade name for it is ‘Red
Baron’ – so it makes the site look very bright and pretty. (So sorry I was so
involved I forgot to take any photos.)
It comes in 25meter x 4meter rolls.
A reasonably convenient size for our particular floor plan, meaning a
few large sheets could be cut rather than lots of little ones. Not an easy material to unfold, but Max helped
and once done the process was quite straight forward. The Red Baron has to be laid to cover the
ground and folded up the wall to meet the damp proof course (DPC) which is the
strip of black waterproof sheet laid in the blockwork, or in our case often on
top of the block work. The DPC sheet has to be a minimum of 150mm up from the
ground level outside the building.
The
Red Baron doesn’t like the cold, it can go brittle and deteriorate if the
temperature falls below zero – so having cut some of it in preparation, it then
had to be folded up again and stored inside over night.
You may think this sounds tedious, it is, and what's more the next day Wednesday, we
had to cut the rest of the sheets so that we would have the whole site ready
for the Building Control inspector who was due on Thursday. Yes indeed, that meant folding all those sheets
up again and storing inside – a much bulkier size than when they were
delivered! Not much room left inside the site office.
Thursday
morning was an early start to get all the cut sheets laid out by 10:00am ready
for the inspection. One development that
had occurred during the week was that the forecast had changed for the worse,
and the temperature for pouring concrete was going to be far too low. The suppliers would not take responsibility for
the concrete, and so we decided to abandon this until the weather has
improved. I did call the Building
Inspector to ask him if he would be happy to see the sheets in place even
though (yet again) we were going to have to take them up, fold them up and store until a
later time. He agreed that this would be
OK as long as he was able to take some photos to have on record.
Up
early we laid the sheets, the inspector arrived, (earring in place) and he gave
us the go-ahead. This is a real help, as
we will now be free to complete this stage without delay as soon as the
temperature rises, and the snow is gone.
So in effect we feel we have basically completed this stage, even though
we had to fold up all those sheets three times. I’m quite conversant now on how to handle the
Red Baron. He doesn’t answer back so
forcefully anymore. He’s been locked
away in the container, with some parts stuffed in the coal bunker where my
tumble drier operates, leaving my office reasonable unencumbered. I hope he survives.
Last
week we had ordered the beam and block floor that is in the raised area of the
living room. The bit that floats over
ground. This all arrived on Wednesday
and the concrete beams were slotted in place between the two steel beams by
Stefan in his big Hi-Mac, and the concrete blocks then placed between the
concrete walls. It makes a good
insta-floor.
Beams arriving by Hi-Mac with blocks in the foreground |
Jake cutting the beams to size, Max and Stefan fitting the concrete beams
between the web of the steelbeams
Some of the concrete beams in place, the concrete blocks are laid between them |
On
Thursday night the promised snow came and was dumped over the site as if it was
pretending to be the concrete slab. It
looked pretty, but not as good as concrete for the purpose intended, so we have
not approved it on inspection. We have
ordered it off site.
On
Friday we received the two quotes we had been waiting for, for the
windows. One was really good – it
provides the specification, and for a very competitive price – the other was
way over the top. However the second lot
have provided a very good quote and specification for a front door that we had
seen at their showrooms that we really like, so both parties may benefit but
for different items.
We
have confirmed the order with the former and so this deserves the promised
bubbles.
We
feel on target.
However,
a slight change of plan to the schedule means that Max and I are halting the
building work for a month whilst we plan for the next stage. It will coincide with the poorer weather and
we feel we can make best use of this time to prepare for the builders so that
we are fully conversant with how the next stage will proceed, and exactly what
materials are needed, and when. Some things will need to be ordered now so that
they are ready to be delivered to site as required. It is most important that once the builders
start they have everything on site in time so that they can be fully
occupied.
So
it may not be as exciting on site over the next few weeks but I’m sure there
will be things to tell you to keep you interested / on tender hooks. . . .
Once
the Red Baron is laid to rest, I will take photos and then more to show the
concrete slab being pumped in over him. From
then on it’s upward and onward.
D-day
gets closer and closer.
No comments:
Post a Comment